Most PMI exams, including PMP, follow a four-option multiple-choice format, with one correct answer.
Example:
๐ก You are managing a project and a stakeholder requests a change that affects the project's cost and schedule. What should you do first?
A) Implement the change immediately.
B) Update the project schedule and inform the team.
C) Evaluate the change request and follow the change control process. โ
D) Reject the request because it affects the baseline.
๐ก A key stakeholder has just joined your project late in the execution phase. What is the best way to involve them?
A) Ignore their input since the project is already in execution.
B) Provide project documents and update them on current progress. โ
C) Ask the team to handle stakeholder concerns.
D) Tell the stakeholder that they cannot influence the project at this stage.